For those wondering how much deeper the massive hole being dug for CPMC’s Cathedral Hill Hospital project will go, the answer is: not much.  In fact, the end of the project’s excavation phase was officially marked this afternoon with a “bottoming out” celebration to commemorate the milestone.

In a couple of weeks, two tower cranes will begin to rise on the site.  And at the end of next month, the new hospital’s foundation will begin to be poured.